Lukashenko: Construction of NPP defined Belarus’ path as high-tech state

Lukashenko: Construction of NPP defined Belarus’ path as high-tech state
An archive photo

MINSK, 14 November (BelTA) – The construction of a nuclear power plant has determined Belarus’ further development as a high-tech state, Belarusian President Aleksandr Lukashenko said at a meeting to discuss the performance of the Belarusian NPP, rising electricity consumption, and proposals for building new nuclear capacities, BelTA has learned.

“Five years ago, when we officially launched the first Belarusian nuclear power plant in Ostrovets, the country entered a new era. The commissioning of the NPP not only strengthened our energy security but also charted Belarus’ future as a high tech state. Having our own nuclear station is, in a certain sense, a way to ensure sovereignty and independence,” the Belarusian leader stated.

He emphasized that safety and reliability have been and remain of the paramount importance at every stage of the plant’s construction and operation.

Aleksandr Lukashenko noted that a five-year period is sufficient to take stock: “We have secured a source of affordable, clean energy for decades to come, achieving both economic and environmental benefits.”

He cited several facts about the performance of the Belarusian Nuclear Power Plant (BelNPP). Greenhouse gas emissions have been reduced by more than 26 million tonnes. Since commissioning, the plant has generated over 53 billion kWh of electricity, allowing Belarus to completely abandon imports. Dependence on natural gas has also been reduced by 14.5 billion cubic meters, with its share in energy generation falling from 95% to about 65%, saving more than $1.6 billion in budgetary funds.

The nuclear plant has also transformed the landscape of Belarusian energy. As part of integrating BelNPP into the power system, a large-scale grid modernization program was carried out: more than 1,700 km of lines were reconstructed, modern substations built, and breakthrough digital technologies introduced to improve reliability of electricity supply.

“A new branch of the economy has been created in the country, along with the necessary infrastructure and a modern system for training personnel. We did not have any of this before. Over the years of implementing the national nuclear energy program, we have accumulated unique expertise in the design, construction, operation, and maintenance of nuclear facilities,” the Belarusian leader emphasized.

BelNPP has also given impetus in electricity consumption. In 2024, consumption reached a record high level of 43.3 billion kWh. Over the past five years, the increase amounted to about 6 billion kWh.

The head of state asked for a brief report on the accumulated experience in operating the nuclear power plant, as well as the results of cooperation with Russian partners in this area and any potential issues that may arise.